Mackerel Islands Stand Alone Power Station

EMC engaged to design and construct solar/battery/diesel microgrid to provide fuel independence and energy savings.

Customer: Mackerel Islands Corporation

Location: Thevenard Island, offshore from Onslow, 1,300 km north of Perth, Western Australia

Features:

  • 324kW Solar PV (ground mount screwpile)
  • 614kWh Sony Lithium Iron Phosphate (2 x 40ft containers)
  • 440kVA Diesel Generation (4 x 110kVA)
  • Corrosive location and high wind (CAT-D) region
  • EMC fully remote monitored and controls